post-fill depending on the grade of the area would be
the preferred mining method. Metallurgical test work
confirmed that the deeper ore is no different from the
shallower ore and that the current plant will be able to
process the underground ore.
The table on the previous pages summarises projected
capital and operating expenditure estimates for the
stand-alone Loulo 0 and Yalea underground project for
the periods indicated.
The board of directors approved the development of
the underground project based on the SRK study.
Subsequent to this, an experienced underground
manager was appointed to advance the development
of the underground project. An internal and external
review of the SRK underground mining plan was also
undertaken with the goal of developing a plan to exploit
both the Yalea and Loulo 0 orebodies optimally as part
of an integrated open pit and underground operation.
As a result of this review, the following changes were
made to the SRK plan and design:
Increase of the resource and reserve base against
the initial study at Yalea and Loulo 0 as well as the
upgrade of inferred to indicated resources as
a result of infill and extensional drilling.
Five additional levels available for stoping at Yalea.
The use of conveyor belts for transporting both waste
and ore from the underground section to surface.
This configuration offers numerous advantages, the
most prominent being the ability to increase
production rates beyond what is possible by
underground fleet transport. There will also be
ventilation and safety benefits.
Decline design incorporating long straight sections
at an inclination of -9 degrees;
The size of the single decline has been changed to
either a single larger (6.5 metre wide and 4.5 metre
high) or two smaller (4.5 metre wide and 4.5 metre
high) declines which provide a better sectional
ventilation intake area and accommodates the
proposed conveyor system. Currently the option of
using a twin decline system is preferred.
Indications at this stage are that while the Loulo 0
boxcut and initial portion of the decline will be
developed simultaneously with the Yalea boxcut
and decline, the focus will be on the development
of the Yalea mine and the Loulo 0 development,
based on ore feed requirements, will be scheduled
later.
Current mine scheduling indicates LOM production
will extend beyond 2020 and will average more than
250 000 ounces per annum.
A site visit by the prospective underground mining
contractors has taken place and award of the
contract is expected towards the end of April 2006.
The capital programme for 2006, estimated at some
US$20 million, has been approved and will allow for site
establishment, purchase of mining equipment and
establishment of the portal and declines. Portal
construction will start in the third quarter and the main
decline development should access first development
ore late 2007.
Randgold Resources    Annual Report 2005 17
2 and 3 Current scheduling indicates LOM production will extend
beyond 2020 and averages more than 250 000 ounces
per annum.