LOULO: ANOTHER STAR IS BORN
Our new mine at Loulo poured its first gold in September
and shipped its first commercial consignment of bullion
four days before its official opening by President Amadou
Toumani Touré of Mali on 12 November. The mine
produced just under 68 000 ounces in the December
quarter at a total cash cost of US$165 per ounce.
While the start up was slightly later than originally
planned, Phase 1 of the plant was sufficiently complete
by the year end to allow steady gold production. This
was a major achievement for our project team,
considering the daunting logistical challenges presented
by the remoteness of the site and the lack of infrastructure
and by the failure of the main plant contractor, which
obliged us to take over the completion of Phase 2, the
hard-rock crushing circuit.
Phase 2 is now scheduled for commissioning in the
second quarter of 2006. Until then, production will be
maintained at planned levels by feeding soft and
screened ore through the Phase 1 circuit. This should
ensure that the delay of the hard rock circuit will not
have a negative effect on Loulo’s operating budget for
the year.
With production from Loulo’s open pit operation now
settled down, the scene is set for the next stage of the
project: the development of an underground operation,
which will not only significantly extend the life and
enhance the value of the mine, but will elevate it to true
world class status. During the course of 2005 SRK
Consulting conducted a feasibility study on the
underground development which confirmed our high
expectations of it. Since then we have completed a
detailed internal and external review of this study and
have fine tuned the original design. We have budgeted
US$20 million for this project in 2006, with portal
construction due to start in the third quarter and the
main decline development commencing in the last
quarter. We expect to access the first development ore
in late 2007.
In the meantime, we have continued to build the resource
base at Loulo, which grew by 24% to 9.9 million ounces
during the year despite the depletion by mining. The
most recent round of deep drilling has returned excellent
results, further defining and expanding the high grade
zones.
MORILA BACK ON TRACK
After a difficult start to the year, with production stuttering
as a result of persistent problems with the plant
expansion project, Morila recovered strongly. Production
of 651 110 ounces was well ahead of forecast and some
140 000 ounces up on 2004, and cash costs were
reasonably well contained at US$221 per ounce.
The remedial measures we initiated at the mine, which
included a change in the management team, are clearly
taking effect, with monthly throughput in the second
half of the year 10% up on the first. The plant is still not
Randgold Resources     Annual Report 2005 7
1 His Excellency, Amadou Toumani Touré, the President of Mali
with Philippe Liétard at the opening of the Loulo Mine on
12 November 2005.
2 First gold pour at Loulo in September 2005.
3 CEO Dr Mark Bristow addresses the dignatories and thousands
of guests at the official opening of Loulo.
4 Local residents in traditional costumes joined in the festivities.